EAp5 Fundamental Refrigerant Management

Avoid refrigerants or inventory, screen and leak-check the applicable tenant refrigerant equipment.1

Points
Required
Applies to
ID+CBD+CO+M
Other versions
v4v4.1

Reviewed · Spot an error? Report it

Points

Required prerequisite; no points. A low inventory GWP alone does not replace the required equipment restrictions, alternative assessment and leak checks.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation: Refrigerant inventory including tenant-controlled existing equipment
  • Preparation: Alternatives assessment for applicable high-GWP refrigerants
  • Preparation: Leak, vacuum, pressure and repair records as applicable
  • Preparation: Cooling and heating system description and no-refrigerant confirmation if using Option 1

Worked example

Assume an inventoried system contains 10 kg of refrigerant with GWP 700. Its contained impact is 10 x 700 = 7,000 kg CO2e, or 7 tCO2e. This is inventory arithmetic, not a credit award or proof that all leak-check obligations were completed.1

Requirements

Option 1 uses no refrigerants in the project. Option 2 inventories equipment installed in scope and existing equipment under tenant control, including refrigerant type, GWP, charge and total GWP. A whole-building inventory is acceptable if tenant systems are included.1

Do not use HCFCs in new equipment. Evaluate alternatives during design for refrigerants above 700 GWP. Before substantial completion, check new and existing refrigerant equipment and repair leaks; field-assembled joints require leak, vacuum and pressure checks before charging.1

FAQ

Is the alternatives assessment triggered at GWP 700 exactly?

The text says GWP greater than 700.1

Can a whole-building refrigerant inventory be used?

Yes, provided tenant systems are included.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.