Prerequisite Fundamental Refrigerant Management

Avoid new CFC- and HCFC-based refrigeration in the fit-out and phase out applicable existing equipment before completion, unless an accepted case-specific extended plan applies.1

Points
Required
Applies to
ID+CBD+C
Other versions
v4v5
VERTIQ reference ID
EAp3

Reviewed · Spot an error? Report it

Points

Required prerequisite; 0 points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: Equipment inventory with equipment type, refrigerant type, charge, installation date and reuse/new status.
  • Preparation checklist: For equipment requiring phaseout, the conversion or replacement plan, refrigerant leakage rate and quantity and phase-out completion date, plus the schedule and narrative for any phaseout extending beyond project completion.

Worked example

Assume the fit-out reuses a large HCFC-charged air-conditioning unit. Its reuse does not satisfy the prerequisite by itself. Identify its charge and refrigerant, document the phaseout/replacement before completion, or obtain acceptance of the extended plan. Separately list any small equipment for which the stated charge exemption applies.1

Requirements

Do not use chlorofluorocarbon (CFC) or hydrochlorofluorocarbon (HCFC) refrigerants in new heating, ventilating, air-conditioning or refrigeration systems. If reusing existing equipment within the project scope, complete a comprehensive CFC/HCFC phaseout before project completion. Base building equipment outside the project purview does not need to be addressed. Extended phaseout plans are considered case by case.12

The Guide exempts qualifying small HVAC units, standard refrigerators and other equipment containing less than 0.5 pound (225 grams) of refrigerant. Identify equipment and charges before applying that exemption.1

FAQ

Does the rule address only CFCs?

No. The ID+C v4.1 text includes HCFCs as well.1

Is every refrigerator automatically exempt?

Check the stated small-equipment and refrigerant-charge conditions rather than assuming an exemption from the equipment name alone.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 Interior Design and Construction GuideNovember 2025 · Fundamental Refrigerant Management prerequisite, printed/PDF pp. 72-72; ID+C scorecard printed/PDF pp. 5-6
  2. LEED v4 Reference Guide for Interior Design and Constructionv4 Reference Guide · Fundamental Refrigerant Management, Behind the Intent and Step-by-Step Guidance; Fundamental Refrigerant Management, Required Documentation table

Maintained by VERTIQ, LEED software for consultants.