Prerequisite Fundamental Refrigerant Management
Avoid CFC refrigerants in new HVAC&R equipment and address CFCs when reusing existing systems.1
- Points
- Required
- Applies to
- ID+CBD+C
- VERTIQ reference ID
- EAp3
Reviewed · Spot an error? Report it
Points
Required prerequisite, with no points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Refrigerant/equipment schedule identifying new, reused and exempt units.
- Preparation checklist: CFC conversion records or a justified extended phase-out proposal where needed.
Worked example
Assume an existing unit contains 0.4 pound of refrigerant. It is below the 0.5-pound small-unit boundary. That exemption does not excuse a separate large reused CFC chiller serving the tenant.1
Requirements
No CFC-based refrigerants may be used in new HVAC&R systems. For reused existing equipment, complete comprehensive CFC conversion before project completion; later phase-out plans are considered on their merits. Existing small units and other equipment containing less than 0.5 pound (225 grams) of refrigerant are exempt.1
FAQ
Does the exemption cover a unit containing exactly 0.5 pound?
The text says less than 0.5 pound; equality is outside that exception.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Fundamental Refrigerant Management; printed and PDF pp. 26
- LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF p.16, February 14, 2025 campus/group clarification
Maintained by VERTIQ, LEED software for consultants.