EAc5 Enhanced Commissioning
Extend commissioning through independent design/construction review, enclosure testing, and/or monitoring-based commissioning.1
Reviewed · Spot an error? Report it
Points
NC maximum 4 points: enhanced MEP 2 and/or enclosure 1; MBCx basic software 1 or enhanced software 2, within the credit cap. Core and Shell maximum 3: enclosure 1 or enclosure plus MEP 2, and MBCx 1.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Independent CxP appointment and commissioning scope
- MEP and enclosure commissioning plans, test records, issues, and training verification
- Three-year MBCx contract or qualified staffing commitment
- MBCx plan, energy-information-system/FDD specifications, and reporting schedule
- Tenant-interconnection commissioning templates for applicable Core and Shell scope
- Final or draft commissioning report, with a list of incomplete tasks and a completion plan if draft
- Owner's project requirements and basis of design
Worked example
Assume NC meets enhanced MEP commissioning for 2 points, enclosure for 1, and enhanced MBCx software for 2. The option subtotal is 2 + 1 + 2 = 5, but the credit is capped at 4. Meeting only software functionality without the required process and term does not establish the MBCx points.1
Requirements
Appoint an independent CxP in predesign or very early design for enhanced commissioning. NC offers MEP systems commissioning under ASHRAE 202-2024 and enclosure commissioning under ASTM E2947-21a with the listed testing and training tasks. Core and Shell's combined enclosure/MEP route includes future tenant-interconnection commissioning templates.1
Monitoring-based commissioning requires at least three years of coordinated implementation beginning no later than occupancy, a documented reporting/review process, staff training, and a remotely accessible energy-information system. NC enhanced software adds the specified diagnostics and analytics requirements; Core and Shell includes expansion and tenant-access provisions.1
FAQ
Can the monitoring-based commitment last one year?
The credit requires a minimum three-year MBCx implementation commitment.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v5 BD+C Rating SystemJuly 2026 · EAc5, printed pp. 114-119