Credit Enhanced Commissioning
Extend fundamental commissioning through enhanced systems, monitoring and/or enclosure work.1
Reviewed · Spot an error? Report it
Points
Enhanced systems Path 1 earns 3 points or monitoring-based Path 2 earns 4; enclosure commissioning adds 2, up to 6 total.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Enhanced commissioning contract and qualifications
- Systems/enclosure commissioning plans
- Training, seasonal test and ten-month review records
- Monitoring points, trend-analysis and correction plan
- List of completed Cx tasks, confirmation of systems manual delivery and ongoing commissioning plan
- Data Centers: verification of the additional design reviews
Worked example
Assume the project fully completes monitoring-based enhanced systems commissioning and qualifying enclosure commissioning. The credit sum is 4 + 2 = 6 points. Do not also add the alternative 3-point systems path.1
Requirements
The qualified CxA needs experience on at least two comparable projects from early design through at least ten months of occupancy. Enhanced systems work includes submittals, manuals, training, seasonal tests, a ten-month operational review and ongoing plan. Monitoring-based work adds defined points, limits, analysis and correction procedures, with at least quarterly first-year analysis. Enclosure commissioning has its own scope, documentation and independent qualified lead. Data Centers add staged design reviews.1
FAQ
Can monitoring be only a dashboard installation?
No. The route also requires procedures, responsibilities, acceptable limits, analysis and corrective actions.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 72-74