Credit Enhanced Commissioning
Extend commissioning beyond the prerequisite through enhanced system commissioning, monitoring and/or envelope commissioning.1
- Points
- 2 to 6 points
- Applies to
- BD+CID+C
- VERTIQ reference ID
- EAc1
Reviewed · Spot an error? Report it
Points
2-6 points: enhanced systems 3 points or enhanced plus monitoring 4; envelope commissioning 2. Eligible system and envelope achievements may be combined within the 6-point cap.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- CxA qualifications and contract
- Enhanced commissioning and monitoring plan
- Submittal/manual/training review records
- Seasonal testing and ten-month review
- Envelope Cx records if pursued
- Ongoing commissioning plan
- Verification of additional design reviews (Data Centers using Option 1)
Worked example
Assume the project completes enhanced systems commissioning with monitoring for 4 points and the separate envelope option for 2. Total = 4 + 2 = 6. Do not add the basic 3-point systems path again.1
Requirements
Use a commissioning authority with the credit's independence and experience qualifications. Enhanced systems commissioning adds submittal review, manuals/training verification, seasonal testing, a ten-month operations review and an ongoing plan. Monitoring-based commissioning adds specified measurement and evaluation procedures, including at least quarterly first-year analyses. Envelope commissioning is a separate eligible option. Data Centers have extra design-review conditions.1
FAQ
Does the monitoring path replace the enhanced commissioning tasks?
No. It requires the enhanced path and adds monitoring-based procedures.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.