Prerequisite Minimum Energy Performance

The energy prerequisite changes for v4 projects registered on or after March 1, 2024.12

Points
Required
Applies to
ID+CBD+C
Other versions
v4.1
VERTIQ reference ID
EAp2

Reviewed · Spot an error? Report it

Points

Required prerequisite, with no points. The 2024 source lists the tenant simulation route; the separate official path resource identifies v4.1 substitution paths, which are not the original v4 prescriptive option.23

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: Registration date, baseline-envelope selection, tenant scope and model input/output report.
  • Preparation checklist: Unregulated-load assumptions, mandatory-provision compliance and renewable accounting; path-selection record where substitutions are proposed.

Worked example

Assume a 2024 Update project using baseline-envelope Sections a-e, with source energy 1,000,000 kWh-equivalent/year baseline and 930,000 proposed. Improvement is 7%, above 6%. The same result would be below the 8% Section f threshold. Mandatory provisions and complete model scope remain separate checks.2

Requirements

For the 2024 Update tenant-level simulation, use ASHRAE 90.1-2010 Appendix G with errata or an approved international equivalent, include all tenant-associated energy, meet mandatory provisions, and document unregulated loads. Use cost, source energy or GHG emissions. Improvement must be at least 6% using baseline-envelope Sections a-e, or 8% using documented existing-condition Section f. On-site renewable energy may be subtracted under G2.4.2

Projects registered before March 1, 2024 use the original criteria. The July 2019 text has a 3% simulation threshold before renewable energy, or a prescriptive path with mandatory/prescriptive compliance, 5% lighting-power reduction and 50% ENERGY STAR eligible rated power. The cumulative addenda remove the original blanket exclusion of existing-condition envelope modeling, citing LI10454; assess that original-route interpretation separately. Do not combine the two editions.124

FAQ

Can a current project simply reuse the old 3% threshold?

No. The official 2024 Update applies to registrations beginning March 1, 2024 and sets its own thresholds.2

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Minimum Energy Performance; printed and PDF pp. 24-25
  2. USGBC LEED v4 ID+C Minimum Energy Performance (2024 Update)2024 Update; current online language checked October 28, 2026 · Option 1 Tenant-Level Energy Simulation
  3. ID+C LEED v4 2024 Energy Update and v4.1 pathsMarch 1, 2024 · PDF pp. 1-2, prescriptive and tenant simulation path comparison
  4. LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF p.16, Reference Guide p.153; April 14, 2017 correction citing LI10454

Maintained by VERTIQ, LEED software for consultants.