Credit Enhanced Commissioning

ID+C enhanced commissioning earns 4 points, or 5 with monitoring-based commissioning.1

Points
See below
Applies to
ID+CBD+C
Other versions
v4.1v5
VERTIQ reference ID
EAc1

Reviewed · Spot an error? Report it

Points

Option 1: 4 points. Option 2: 5 total, not 4 plus 5.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: CxA independence and experience evidence; enhanced commissioning plan and submittal reviews.
  • Preparation checklist: Training/manual delivery, seasonal tests, ten-month review, ongoing plan and monitoring records if used.

Worked example

Assume Option 1 is complete and the monitoring procedures, points and quarterly analyses are also complete. The monitoring option is 5 points total. Four quarterly analyses over one year illustrate the minimum analysis frequency, but do not establish the remaining tasks.1

Requirements

Use the enhanced CxA independence criteria stated with Fundamental Commissioning and Verification. Option 1 adds contractor-submittal review, systems-manual and training requirements and verification, seasonal testing, a ten-month operations review and an ongoing commissioning plan.1

Option 2 includes Option 1 and monitoring-based procedures for energy/water systems, measurement points, responsibilities, trends, acceptable values, fault correction and training. Analyze at least quarterly during the first occupancy year and update the systems manual for changes.1

FAQ

Is envelope commissioning the second ID+C option?

No. In this ID+C text Option 2 is monitoring-based commissioning; the addenda remove the BD+C envelope-agent exception from ID+C guidance.12

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Enhanced Commissioning; printed and PDF pp. 27-28