Prerequisite Fundamental Refrigerant Management

Avoid CFC- and HCFC-based refrigerants in new HVAC&R equipment and address existing equipment.1

Points
Required
Applies to
BD+CID+C
Other versions
v4v5
VERTIQ reference ID
EAp4

Reviewed · Spot an error? Report it

Points

Required prerequisite; no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • HVAC&R equipment and refrigerant inventory
  • Manufacturer refrigerant declarations
  • Existing-system phase-out/conversion records

Worked example

Assume a reused existing unit contains 2 kg of HCFC refrigerant. It exceeds the 0.225 kg small-unit exemption and needs a compliant phase-out/conversion response; its small cooling capacity alone does not establish an exemption.1

Requirements

New systems cannot use CFC or HCFC refrigerants. When existing equipment is reused, complete a comprehensive phase-out conversion before project completion; longer plans are considered on their merits rather than automatically accepted. The cited small-equipment exemption is for existing units and other equipment containing less than 0.5 lb (225 g) refrigerant.1

FAQ

Does this mean every HFC refrigerant earns the enhanced credit?

No. This prerequisite's ozone-depleting refrigerant rule is separate from the enhanced credit's GWP and impact requirements.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 71

Maintained by VERTIQ, LEED software for consultants.