Credit Enhanced Refrigerant Management
Reduce refrigerant life-cycle impacts through no or low-impact refrigerants, or the specified refrigerant-impact calculation. Retail commercial refrigeration has additional conditions.1
Reviewed · Spot an error? Report it
Points
1 point. The options are alternatives, and Retail refrigeration conditions are additional to HVAC compliance.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: HVAC/refrigeration inventory, refrigerant ODP/GWP, charge, capacity and life-cycle calculation inputs.
- Preparation checklist: Refrigerant management and leak-test records; Retail commercial refrigeration calculations or qualifying GreenChill evidence.
- Preparation checklist: For Option 2, confirmation that project HVAC&R systems comply with ASHRAE Standard 15 and equipment tags per drawings.
Worked example
Assume two Option 2 systems have IP life-cycle impact results of 80 and 120 and capacities of 30 and 10 tons. Weighted result = (80 x 30 + 120 x 10) / (30 + 10) = 90, below the IP limit of 100. This demonstrates only the weighted impact test, assuming the component calculations and other requirements are valid.1
Requirements
For Commercial Interiors and Hospitality, Option 1 uses no refrigerants, or only refrigerants with ozone depletion potential of zero and global warming potential below 50. Option 2 applies ASHRAE 15-2019, a refrigerant-management plan for systems with more than 0.5 pound (225 grams), and the capacity-weighted refrigerant-impact limit for new and existing base-building and tenant equipment serving the project.1
For Option 2, the combined LCGWP + LCODP x 100,000 result must be no greater than 100 in the Guide IP calculation or 13 in its SI calculation. Use the corresponding charge, leakage, end-of-life, life and cooling-capacity units throughout.1
Retail meets Option 1 or 2 for HVAC systems. Commercial refrigeration also needs zero ODP, average HFC charge no greater than 1.75 pounds per 1,000 Btu/h evaporator cooling load, predicted annual refrigerant emissions no greater than 15%, and the specified leak-tightness test. The Guide alternatively permits qualifying GreenChill silver-level certification for newly constructed stores.1
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 Interior Design and Construction GuideNovember 2025 · Enhanced Refrigerant Management, printed/PDF pp. 91-94; ID+C scorecard printed/PDF pp. 5-6