PRc1 Project Priorities

Combine eligible regional, project-type, exemplary-performance, pilot or approved innovation achievements for up to 9 points.1

Points
Up to 9
Applies to
ID+CBD+CO+M

Reviewed · Spot an error? Report it

Points

Maximum 9 points across eligible achievements. The Rating System does not automatically award one point to every submitted idea; use the applicable credit requirements and approved award.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation: Current applicable Credit Library requirements and achievement evidence
  • Preparation: Innovation baseline, measurable results and multi-component scope if proposed
  • Preparation: Project-type or regional narrative and submittals, or pilot credit registration, survey and submittals, as applicable

Worked example

Assume three eligible priority achievements have documented awards of 2, 3 and 1 points. Their total is 6, below the 9-point cap. These assumed awards must each be supported by their own applicable credit or approval; submitting three proposals alone does not earn 6 points.1

Requirements

Use applicable credits from USGBC's Credit Library for regional priority, project type, exemplary performance or pilot achievements. Innovation must achieve significant measurable performance through a strategy not already addressed in the rating system and identify intent, compliance requirements, submittals and the design approach.1

The July addendum's innovation criteria require quantitative improvement against a baseline, a comprehensive whole-project strategy with at least two components, and performance significantly beyond standard sustainable practice. A single product is not a complete innovation strategy.2

FAQ

Is purchasing one innovative product automatically an innovation credit?

No. The July explanation requires a comprehensive whole-project strategy with at least two components.2

Can ten approved points be added to this credit?

The credit total is capped at 9.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 ID+C Rating SystemJuly 2026 · PRc1; printed pp. 107-108, PDF pp. 112-113; scorecard printed pp. 1-2, PDF pp. 6-7
  2. LEED v5 ID+C Addenda Table, cumulativeJuly 31, 2026; individual post dates identified in locator · PDF p. 10, PRc1 Credit Library terminology and innovation-strategy criteria; July 31, 2026

Maintained by VERTIQ, LEED software for consultants.