LTc3 Electric Vehicles

Use qualifying base-building EV credit achievement or provide compliant charging capacity against the properly allocated project parking denominator.12

Points
See below
Applies to
ID+CBD+CO+M

Reviewed · Spot an error? Report it

Points

Maximum 2 points using either option. Apply the separately stated residential parking thresholds if that row is relevant to the project; do not substitute the commercial row automatically.1

Exemplary performance: doubling the highest EVSE parking threshold under Option 2 earns 1 exemplary performance point, claimed under Project Priorities (EP5).3

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation: Base-building EV credit evidence or installed-EVSE schedule
  • Preparation: Building parking count and allocation basis
  • Preparation: Electrical/connected-functionality and accessible-space drawings

Worked example

Assume 50 commercial parking spaces are allocated to the project under the July 31 addendum, with the EVSE spaces dedicated to this project and not double-counted. The 2-point threshold is max(10% x 50, 4) = 5 installed compliant EVSE spaces. The required EVSE must meet the electrical, connected-functionality and accessible-installation requirements.12

Requirements

Option 1 relies on the specified EV/green-vehicle credit earned under an eligible LEED-certified base building and converts its award through Table 1. Option 2 provides installed EVSE under Table 2.1

Option 2 EVSE must meet Level 2/3, voltage, connected-functionality and time-of-use-response criteria. Provide at least one accessible charging space at least 8 ft wide with a 5-ft access aisle and the described mobility/visual accessibility features. For commercial parking, meet at least 5% or two spaces for 1 point, or 10% or four for 2, whichever count is greater.1

The July 31 addendum requires EVSE spaces to be dedicated to this project and not counted toward another LEED project. Include parking used by the project even outside its boundary; where parking is shared, use only the project allocation and document the rationale. Exclude on-street public parking and ineligible fleet/inventory parking.2

FAQ

Is the minimum always four charging spaces for two points?

No. The commercial 2-point requirement is the greater of 10% of parking or four spaces.1

Can charging-ready conduit substitute for installed EVSE in Option 2?

The stated ID+C option requires installed qualifying EVSE, not only future readiness.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 ID+C Rating SystemJuly 2026 · LTc3; printed pp. 19-20, PDF pp. 24-25; scorecard printed pp. 1-2, PDF pp. 6-7
  2. LEED v5 ID+C Addenda Table, cumulativeJuly 31, 2026 · PDF p. 3, LTc3 Further Explanation, Calculating provided capacity, July 31, 2026; applies the allocation guidance to both options
  3. USGBC LEED credit library: Electric Vehicles: Exemplary Performance (EP5)Published Apr 22, 2025; retrieved November 8, 2026 · EP5 requirements