Limit exterior uplight, backlight, glare, and internally illuminated signage for the project's lighting zone and installation geometry.1

Points
See below
Applies to
BD+C
Other versions
v4v4.1

Reviewed · Spot an error? Report it

Points

NC and Core and Shell: 1 point for all applicable requirements. Maximum uplight ratings are U0 in LZ0/LZ1, U2 in LZ2, U3 in LZ3, and U4 in LZ4; also satisfy the separate backlight/glare table.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Exterior lighting plan and MLO lighting-zone determination
  • Luminaire schedule and BUG photometric reports for the installed sources
  • Lighting-boundary, mounting-height, distance, and orientation calculation
  • Exemption and separate-control schedule; internally illuminated signage details with evidence of maximum nighttime luminance

Worked example

Assume a site is validly classified LZ2 and all applicable luminaires have U1. Because U1 is below the U2 cap, the uplight check passes. This does not establish backlight, glare, or signage compliance; these require separate review.1

Requirements

Apply the MLO lighting-zone uplight limits and the backlight/glare limits determined by mounting height, distance from the lighting boundary, and orientation. Address all exterior luminaires inside the project boundary. The listed exemptions apply only when separately controlled; an exempt light is not a blanket exemption for the whole site. Internally illuminated exterior signage must also stay within the nighttime luminance limits in Table 3: 50 cd/m² in LZ0 and LZ1, 100 in LZ2, 200 in LZ3, and 350 in LZ4.1

FAQ

Can one acceptable BUG rating be applied to the entire site?

No. Check each applicable luminaire's installed source and location against the zone and geometry criteria.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · SSc6, printed pp. 51-53

Maintained by VERTIQ, LEED software for consultants.