Credit Light Pollution Reduction
Meet both uplight and light-trespass limits and the applicable exterior-signage requirement.1
- Points
- 1 point
- Applies to
- BD+C
- VERTIQ reference ID
- SSc6
Reviewed · Spot an error? Report it
Points
1 point.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Exterior lighting plan and MLO zone justification
- IES photometric files with installed tilt/orientation
- BUG schedule, or calculations of lumens above horizontal and boundary vertical illuminance
- Signage luminance and control specifications
Worked example
Assume a luminaire is 6 m from the lighting boundary and its mounting height is 4 m. The ratio is 6/4 = 1.5 mounting heights, so use the 1-to-2-height row when assessing the applicable BUG criteria. Lighting zone, orientation and all other luminaires still need review.1
Requirements
Establish the project's MLO lighting zone and lighting boundary. Use BUG ratings or calculations for uplight and trespass; the two components may use different methods. Evaluate installed orientation and tilt, boundary distance, allowed exemptions and separate controls. Internally illuminated signs must meet the stated daytime and nighttime luminance limits even though signage is listed separately from other exterior-luminaire requirements.1
FAQ
Can passing uplight alone earn the credit?
No. Light trespass and the applicable signage requirement must also pass.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.