Credit Light Pollution Reduction

Meet both uplight and light-trespass limits and the applicable exterior-signage requirement.1

Points
1 point
Applies to
BD+C
Other versions
v4v5
VERTIQ reference ID
SSc6

Reviewed · Spot an error? Report it

Points

1 point.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Exterior lighting plan and MLO zone justification
  • IES photometric files with installed tilt/orientation
  • BUG schedule, or calculations of lumens above horizontal and boundary vertical illuminance
  • Signage luminance and control specifications

Worked example

Assume a luminaire is 6 m from the lighting boundary and its mounting height is 4 m. The ratio is 6/4 = 1.5 mounting heights, so use the 1-to-2-height row when assessing the applicable BUG criteria. Lighting zone, orientation and all other luminaires still need review.1

Requirements

Establish the project's MLO lighting zone and lighting boundary. Use BUG ratings or calculations for uplight and trespass; the two components may use different methods. Evaluate installed orientation and tilt, boundary distance, allowed exemptions and separate controls. Internally illuminated signs must meet the stated daytime and nighttime luminance limits even though signage is listed separately from other exterior-luminaire requirements.1

FAQ

Can passing uplight alone earn the credit?

No. Light trespass and the applicable signage requirement must also pass.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 42-45