LTc1 Sensitive Land Protection

Place the development footprint on previously developed land or demonstrate that a previously undeveloped location avoids the specified sensitive lands.1

Points
1 point
Applies to
BD+C
Other versions
v4v4.1

Reviewed · Spot an error? Report it

Points

NC and Core and Shell: 1 point through either alternative.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Development footprint and site-boundary plan
  • Historic land-use or previously developed site evidence
  • Floodplain, habitat, soil/farmland, water-body, wetland, and slope records, verification narrative, and sensitive-land-avoided area calculation for Option 2

Worked example

Assume the entire 2,000 m² development footprint is documented as previously developed. The footprint coverage is 2,000/2,000 = 100%, illustrating Option 1's location test. This example assumes the historical development evidence establishes the defined status.1

Requirements

Option 1 uses previously developed land. Option 2 screens prime farmland, floodplains, notable habitat, water bodies, wetlands, and steep slopes using the defined local or international equivalents. Water-body and wetland buffers are 100 feet (30 m) and 50 feet (15 m), with limited minor-improvement exceptions. Apply the slope-protection criteria where relevant; site location alone does not waive them.1

Wetlands and water bodies that do not need protection for this credit, along with their buffers, are: man-made water bodies that lack natural edges and floors or native ecological communities in the water and along the edge, such as industrial mining pits, concrete-lined canals or stormwater retention ponds; man-made linear wetlands that result from the interruption of natural drainages by existing rights-of-way; and wetlands made incidentally and rated poor for all measured wetland functions by a qualified biologist, using a method accepted by state or regional permitting agencies or a local equivalent outside the U.S.2

FAQ

Does a previously undeveloped site automatically fail?

No. Option 2 allows qualifying sites that satisfy the sensitive-land screening and protection criteria.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · LTc1, printed pp. 16-17
  2. LEED v5 BD+C AddendaJuly 31, 2026 · LTc1: Sensitive Land Protection, Further Explanation, Option 2, Wetlands and Water Bodies, Addenda p. 2 (Reference Guide p. 54)

Maintained by VERTIQ, LEED software for consultants.