EAp2 Minimum Energy Efficiency

LEED v5 BD+C EAp2 requires compliance with ASHRAE 90.1-2019 with addendum cr or ASHRAE 90.1-2022; the 2022 option becomes mandatory for projects registering on or after January 1, 2028.1

Points
Required
Applies to
BD+CID+C

Reviewed · Spot an error? Report it

Points

This is a required prerequisite for New Construction and Core and Shell, with no points awarded.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Energy model input and output report identifying the selected ASHRAE edition, compliance path and results, if a simulation path is used.
  • Building drawings and equipment schedules supporting the envelope, lighting and HVAC inputs used in the compliance assessment.
  • Calculation report documenting the selected metric, conversion factors and applicable BPF table.
  • ASHRAE 90.1 mandatory-provisions compliance documentation, plus compliance forms or a COMcheck report for the prescriptive method.

Worked example

Illustrative input: 100,000 kWh of electricity. Applying the specified U.S. future-source factor of 2.0 gives 200,000 kWh of future source energy (100,000 × 2.0). This arithmetic isolates one conversion; a compliant Appendix G submission must also use the applicable BPFs and account for all relevant energy uses.1

Requirements

Before January 1, 2028, choose Option 1 (90.1-2019 with addendum cr) or Option 2 (90.1-2022), using an applicable Section 4.2 compliance path.1

For the Appendix G path, future source energy can replace cost with the corresponding Rating System BPF table; the 2022 option also permits site or source energy documented using Informative Appendix I.1

The future-source electricity factor is 2.0 for the U.S.; a lower national average may be used where applicable outside the U.S.1

FAQ

Can a project still choose ASHRAE 90.1-2019?

Yes, for registration before January 1, 2028, provided the project follows Option 1, including addendum cr; registrations on or after that date must use Option 2.1

Is a future-source conversion enough to show compliance?

No. The conversion is part of the applicable Appendix G compliance method and must be paired with the appropriate Rating System BPF table.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · EAp2, printed pp. 78-80 (PDF pp. 85-87), Options 1-2 and Tables 1-2

Maintained by VERTIQ, LEED software for consultants.