Prerequisite Indoor Water Use Reduction

Reduce in-scope fixture water use by 20% and meet the applicable appliance and process standards.1

Points
Required
Applies to
ID+CBD+C
Other versions
v4.1
VERTIQ reference ID
WEp1

Reviewed · Spot an error? Report it

Points

Required prerequisite, with no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: Fixture schedule, label evidence, occupancy/use assumptions and water calculations.
  • Preparation checklist: In-scope appliance/process schedule and cutsheets; reused-equipment scope record where relevant.

Worked example

Assume an applicable fixture calculation has 100,000 gallons/year baseline and 78,000 proposed, using identical occupant/use assumptions. Reduction is (100,000-78,000)/100,000 = 22%, above 20%. That calculation does not establish labeling or process-equipment compliance.1

Requirements

Use Table 1 baselines to demonstrate at least 20% aggregate fixture/fitting reduction. Newly installed eligible toilets, urinals, private lavatory faucets and showerheads must carry WaterSense or a local equivalent outside the U.S., and projects outside the U.S. must meet WaterSense flush and flow rates. Projects with no fixtures or fittings within the tenant spaces are exempt from this prerequisite.21

Within the project scope, meet the appliance and process requirements in Tables 2-3, including efficient appliances, prerinse spray valves at no more than 1.3 gpm, and no once-through potable-water cooling. Retail/Hospitality also apply Tables 4-5 for kitchen equipment and processes. Existing appliances and equipment reused in the project are not required to meet Tables 2-3.2

FAQ

Is the credit calculation boundary always the same?

No. The prerequisite addresses tenant-space scope and has a no-fixtures exception; the credit includes fixtures needed by occupants, even outside the tenant space.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Indoor Water Use Reduction; printed and PDF pp. 16-18
  2. LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF pp. 9-10, Reference Guide pp. 93-94; reused-equipment exceptions and February 20, 2026 documentation wording; PDF pp. 9-10, Reference Guide pp. 93-94; reused-equipment exceptions, International Tips and February 20, 2026 documentation wording

Maintained by VERTIQ, LEED software for consultants.