Prerequisite Minimum Indoor Air Quality Performance

Meet the ID+C ventilation and outdoor-air monitoring requirements for every applicable ventilation mode.1

Points
Required
Applies to
ID+CBD+C
Other versions
v4.1
VERTIQ reference ID
EQp1

Reviewed · Spot an error? Report it

Points

Required prerequisite, with no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: Space/system ventilation calculations, occupancy and engineering assessment if constrained.
  • Preparation checklist: Outdoor-air monitoring sequence, sensor specifications and natural/mixed-mode design evidence where applicable.
  • Preparation checklist: PM2.5 and ozone nonattainment status, with MERV 11 filter confirmation, or the JIS alternative in Japan, where the project is in a PM2.5 nonattainment area.

Worked example

Assume a VAV outdoor-air design minimum of 1,000 cfm. A 15% deviation is 150 cfm, so 850 or 1,150 cfm reaches the alarm boundary. The measurement accuracy requirement is separate from that alarm setting; ventilation sizing and system-scope checks remain necessary.1

Requirements

For mechanically ventilated spaces, use ASHRAE 62.1-2010 ventilation-rate procedure and Sections 4-7, or a more stringent local equivalent; outside-U.S. projects have the stated EN 15251/EN 13779 alternative. If physical constraints prevent the required airflow, document an engineering assessment and supply the maximum feasible flow, at least 10 cfm/person.1

For natural ventilation, demonstrate effective design using the specified ASHRAE natural-ventilation provisions and CIBSE AM 10 decision process. Projects in Europe may instead use the published Europe alternative: a design study comparing natural and mechanical ventilation, the stated minimum ventilation areas, and the same monitoring requirements. The ASHRAE IAQ procedure is not a compliance route. Apply monitoring appropriate to VAV, constant-volume, natural and mixed-mode operation. In-scope VAV outdoor intakes require measurement accurate to +/-10% of design minimum and an alarm at 15% deviation.21

FAQ

Can the ASHRAE IAQ procedure replace the ventilation-rate procedure?

The ID+C prerequisite expressly excludes the IAQ procedure as its compliance method.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Minimum Indoor Air Quality Performance; printed and PDF pp. 52-53
  2. LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF p.51, April 6, 2018 Europe ACP, April 10, 2020 Table 1 update and Japan JIS filter entry

Maintained by VERTIQ, LEED software for consultants.