Prerequisite Minimum Indoor Air Quality Performance
Provide the minimum outdoor-air ventilation and monitoring required for the actual tenant ventilation system. Mechanical and natural ventilation follow separate ID+C compliance paths.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; 0 points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Tenant ventilation zoning, occupancy, outdoor-air calculations and applicable standard sections.
- Preparation checklist: Testing/balancing and monitor/alarm specifications; existing-system assessment or natural-ventilation calculations where applicable.
- Preparation checklist: PM2.5 and ozone non-attainment status, with confirmation of MERV 11 or equivalent filters and ozone air cleaning where applicable.
Worked example
Assume an in-scope mechanical system has a design minimum outdoor-air setpoint of 2,000 cfm. A 15% deviation is 2,000 x 0.15 = 300 cfm. Configure the required alarm to indicate a deviation of at least 300 cfm from the setpoint, and verify the measuring accuracy separately. This example does not establish the design ventilation rate itself.1
Requirements
Mechanically ventilated spaces meet ASHRAE 62.1-2016, Sections 4, 5, 6.2, 6.5 and 7, or a local equivalent, whichever is more stringent. Projects outside the U.S. may instead meet ISO 17772-1:2017, Section 6.3, using Method 1 with Category I or II, and a local ventilation design standard such as EN 16798-3:2017, Sections 7-10. Where physical constraints of an existing system make the required rates infeasible, obtain an engineering assessment, supply the maximum possible toward the standard rate, and provide no less than 10 cfm/person (5 L/s-person). This is not a general permission to select a lower rate. Projects outside the U.S. are considered in a non-attainment area for PM2.5 and ozone unless local government outdoor air quality data shows otherwise; for non-attainment projects, confirm MERV 11 or equivalent filters before occupancy and ozone air cleaning where ozone levels exceed the applicable standard.12
For mechanical systems within project scope with outdoor-air intake greater than 1,000 cfm (472 L/s), monitor minimum outdoor airflow with the specified +/-10% accuracy and an alarm for deviations of at least 15% from the setpoint. Eligible constant-volume systems without demand-control ventilation may use the specified damper-position indicator.1
Naturally ventilated spaces follow one of the three listed ASHRAE 62.1-2016 addendum l prescriptive, engineered or existing-building paths and a permitted monitoring strategy. The direct-exhaust strategy is unavailable to the existing-building Option 3. The ASHRAE IAQ Procedure in Section 6.3 cannot be used for this prerequisite.1
For natural ventilation, the permitted monitoring choices are qualifying direct exhaust airflow measurement, automatic indication that required openings remain open during occupied hours, or CO2 monitoring in each thermal zone. The exhaust device uses +/-10% accuracy and at least 15% deviation alarm; CO2 monitors are 3-6 ft above the floor and alert for a concentration more than 10% above the calculated setpoint. The direct-exhaust strategy is unavailable for existing-building Option 3.1
FAQ
Can any existing system simply use 10 cfm per person?
No. The constrained-system case needs the engineering assessment and maximum feasible delivery toward the standard minimum.1
Can the ASHRAE IAQ Procedure replace these ventilation paths?
No. The Guide explicitly excludes Section 6.3 IAQ Procedure for this prerequisite.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 Interior Design and Construction GuideNovember 2025 · Minimum Indoor Air Quality Performance prerequisite, printed/PDF pp. 138-141; ID+C scorecard printed/PDF pp. 5-6
- LEED v4.1 Interior Design and Construction Addenda Table, first editionNovember 3, 2025 cumulative table · Regional ACP > ISO and EN standards, addenda table p.100
Maintained by VERTIQ, LEED software for consultants.