Prerequisite Minimum Indoor Air Quality Performance
Meet ventilation and monitoring requirements for the project's systems and adaptation.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Ventilation calculations and mechanical plans
- Room population/area schedule
- Controls and airflow-monitoring sequence
- Healthcare ventilation and residential/radon documents where applicable
Worked example
Assume a system's required outdoor-air setpoint is 1,000 L/s. A 15% deviation corresponds to 150 L/s. Where the source's airflow-monitoring rule applies, the alarm must identify deviations of that size; this is not a substitute for calculating the correct minimum ventilation.1
Requirements
Mechanically ventilated spaces use the specified ASHRAE 62.1-2010 procedures or a more stringent local equivalent; projects outside the U.S. may instead use the specified CEN EN 15251-2007 and EN 13779-2007 path. Natural and mixed-mode spaces must satisfy the natural-ventilation provisions and demonstrate suitability using the cited CIBSE guidance. Provide the applicable airflow/opening/CO2 monitoring. Healthcare uses its more stringent applicable 170/FGI/local criteria; Core and Shell systems must be capable of meeting projected tenant ventilation and monitoring levels; any project with residential units adds the specified dwelling-unit conditions.1
FAQ
Does a CO2 sensor alone prove adequate ventilation?
No. Minimum ventilation design and the applicable monitoring strategy are separate requirements.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 BD+C Rating SystemUpdated July 25, 2019 · Minimum Indoor Air Quality Performance prerequisite, printed/PDF pp. 106-109