Provide glare control and meet one complete daylight simulation or measurement route.1
Reviewed · Spot an error? Report it
Points
Choose one route, maximum 3 points. The same area percentage can carry different points under simulation and measurement.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Glare-control design, regularly occupied area and model/measurement plan.
- Preparation checklist: Annual sDA/ASE report or complete illuminance model/measurements with grid, dates, weather and FF&E evidence.
Worked example
Assume Option 1 annual simulation shows 60% sDA and 8% ASE under the required calculation setup. The sDA lies above 55% but below 75%, so it corresponds to 2 points, provided glare control and all remaining modeling conditions are met.1
Requirements
For all regularly occupied spaces provide manual glare control, or automatic control with manual override. Museum exhibit and other collection spaces may be excluded from the daylight requirements. Option 1 uses annual sDA300/50% and ASE 1000,250, including furniture and permanent obstructions, an hourly weather analysis and the specified grid/work-plane setup. Table 1 awards 2 points at 55% sDA or 3 at 75%; ASE must be no more than 10% of the daylit area used in that calculation.21
Option 2 models 300-3,000 lux at 9 am and 3 pm under the specified equinox clear-sky method, earning 1/2 points for 75%/90% qualifying area. Option 3 measures 300-3,000 lux with FF&E installed and the specified grids and two-season timing, earning 2/3 points for 75%/90%.1
FAQ
Does 75% qualifying area always mean the same point value?
No. Annual sDA75%=3, equinox simulation 75%=1, and measurement 75%=2.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Daylight; printed and PDF pp. 70-72
- LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF p.49, July 29, 2022 Museums entry
Maintained by VERTIQ, LEED software for consultants.