Credit Indoor Air Quality Assessment
Choose flush-out or air testing after construction and cleaning; the two options cannot be combined.1
Reviewed · Spot an error? Report it
Points
Flush-out 1 point or air testing 2; select one option.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Selected-path plan and completion/cleaning record.
- Preparation checklist: Flush-out flow/temperature/humidity logs and filter records, or full test report with lab accreditation certificate and scope.
Worked example
Assume a 10,000-square-foot project uses the before-occupancy flush-out path. Required outdoor-air volume is 10,000 x 14,000=140,000,000 cubic feet. At an assumed constant 10,000 cfm this is 14,000 minutes, or 233.33 hours. This is a volume/time illustration only: temperature, humidity, cleaning, filters and actual delivered flow must also comply.1
Requirements
Install all finishes and movable furnishings and finish major VOC punch-list work. Flush-out requires new filters and 14,000 cubic feet of outdoor air per square foot with 60-80 F indoor temperature and relative humidity no more than 60%. Early occupancy can begin after 3,500 cf/sf, with the specified ongoing ventilation and three-hour preoccupancy start until the total is delivered.1
Air testing uses the listed current methods and concentration limits under normal occupied ventilation before occupancy; Retail may test within 14 days of occupancy. Accredited labs are required for formaldehyde/VOC analysis. Correct and retest noncompliant contaminants at the same locations. Include accreditation certificate/scope with the testing report per February 2026 addenda.12
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Indoor Air Quality Assessment; printed and PDF pp. 63-65