Credit Construction Indoor Air Quality Management Plan
Implement an IAQ protection plan during construction and before occupancy.1
Reviewed · Spot an error? Report it
Points
1 point.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Construction IAQ plan, responsibilities and protection records/photos.
- Preparation checklist: Temporary/final filter specifications and installation/replacement logs.
Worked example
Assume a permanent air handler must operate while fit-out work continues. A MERV 8 temporary filter at every required return opening with no bypass meets only the temporary-filtration component. Final filter replacement, moisture protection, tobacco control and the implemented SMACNA measures remain necessary.1
Requirements
Meet applicable SMACNA 2007 Chapter 3 control measures and protect absorptive materials from moisture. Do not operate permanent air handlers during construction unless at least MERV 8 or stated-equivalent media protect return/transfer openings with no bypass. Projects in Japan may use E(4) 60% under JIS B 9908:2011 as the alternative to MERV 8. Replace media with final-design filters immediately before occupancy.21
Prohibit tobacco inside and within 25 feet (7.5 meters) of the entrance during construction.1
FAQ
Can final filters simply remain in place after construction?
The credit calls for replacement with final-design filtration media immediately before occupancy.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 for Interior Design and ConstructionUpdated July 25, 2019 · Construction Indoor Air Quality Management Plan; printed and PDF pp. 62
- LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · PDF p.51, April 10, 2020 Japan JIS filter entry
Maintained by VERTIQ, LEED software for consultants.