Credit Construction Indoor Air Quality Management Plan
Implement a construction and preoccupancy IAQ plan that controls pollutants, protects absorptive materials and manages HVAC filtration and smoking.1
Reviewed · Spot an error? Report it
Points
1 point for implementing the required plan and controls.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Construction/preoccupancy IAQ plan highlighting the nonsmoking policy, narrative of absorbent-material protection, site inspections and annotated photographs of each IAQ measure.
- Preparation checklist: Temporary/final filter specifications and replacement records, HVAC operation controls and smoking-policy implementation.
Worked example
Assume the contractor needs the permanent air system for construction conditioning. Before use, protect each return/transfer opening with the required temporary filters and inspect for bypass. Keep moisture-sensitive materials dry, enforce the construction smoking rule, and replace the temporary filters with final design media immediately before occupancy. Record implementation, not only the written plan.1
Requirements
Meet or exceed applicable recommended control measures in SMACNA IAQ Guidelines for Occupied Buildings under Construction, second edition, Chapter 3. Protect stored and installed absorptive materials from moisture damage.1
Do not operate permanent air-handling equipment during construction unless each return grille and return/transfer duct opening has MERV 8 filtration or the stated ISO coarse 90% alternative, installed without bypass. Immediately before occupancy, replace filtration media with the final design media per manufacturer instructions.1
Prohibit smoking inside and within 25 ft (7.5 m) of building openings during construction. The smoking definition includes electronic devices and the stated combustion sources.1
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.