Prerequisite Fundamental Commissioning and Verification
Commission the specified energy- and water-related systems and document their operation.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- OPR and BOD
- CxA appointment and qualifications
- Commissioning plan, test records and issue log
- Final Cx report and facilities O&M plan
Worked example
Assume ten required system tests are scheduled and nine are verified. Completion is 9 / 10 = 90%, but the prerequisite is not awarded on a percentage basis. Resolve and document the remaining required test and issues.1
Requirements
Engage a qualified commissioning authority by the end of design development. Develop OPR, BOD, a commissioning plan, checklists and test procedures; verify testing; maintain the issues log and final report; report findings directly to the owner. Address the exterior enclosure in the required design review and maintain current facilities requirements and an operations/maintenance plan. CxA independence and small-project rules vary.1
FAQ
Does hiring a commissioning authority alone satisfy the prerequisite?
No. The documented commissioning activities, testing, reports and operational plan must also be completed.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 BD+C Rating SystemUpdated July 25, 2019 · Fundamental Commissioning and Verification prerequisite, printed/PDF pp. 63-64
Maintained by VERTIQ, LEED software for consultants.