Prerequisite Fundamental Commissioning and Verification

Commission relevant systems and prepare an operating plan for the building.1

Points
Required
Applies to
BD+CID+C
Other versions
v4
VERTIQ reference ID
EAp1

Reviewed · Spot an error? Report it

Points

Required prerequisite; no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Owner's Project Requirements and Basis of Design
  • Commissioning plan, checklists and functional test records
  • Issues log and final commissioning report
  • Current facilities requirements/O&M plan
  • Commissioning authority previous experience

Worked example

Assume functional testing records a control fault on one of four air systems. Completing four test forms is insufficient: record the fault in the issues log, communicate it to the owner and document findings and recommendations in the final commissioning report.1

Requirements

Develop the OPR and BOD, engage a qualified commissioning authority, implement the commissioning plan, check construction requirements, verify tests, maintain issues/findings and report to the owner. The scope covers relevant mechanical, electrical, plumbing and renewable systems; enclosure scope here includes OPR/BOD and design review. Prepare a current facilities requirements/O&M plan covering schedules, setpoints, ventilation, systems, preventive maintenance and ongoing commissioning.1

FAQ

Is equipment startup alone enough?

No. The prerequisite describes an owner-facing commissioning process with design review, testing, issues documentation and operating information.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.