Prerequisite Fundamental Commissioning and Verification
Commission relevant systems and prepare an operating plan for the building.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Owner's Project Requirements and Basis of Design
- Commissioning plan, checklists and functional test records
- Issues log and final commissioning report
- Current facilities requirements/O&M plan
- Commissioning authority previous experience
Worked example
Assume functional testing records a control fault on one of four air systems. Completing four test forms is insufficient: record the fault in the issues log, communicate it to the owner and document findings and recommendations in the final commissioning report.1
Requirements
Develop the OPR and BOD, engage a qualified commissioning authority, implement the commissioning plan, check construction requirements, verify tests, maintain issues/findings and report to the owner. The scope covers relevant mechanical, electrical, plumbing and renewable systems; enclosure scope here includes OPR/BOD and design review. Prepare a current facilities requirements/O&M plan covering schedules, setpoints, ventilation, systems, preventive maintenance and ongoing commissioning.1
FAQ
Is equipment startup alone enough?
No. The prerequisite describes an owner-facing commissioning process with design review, testing, issues documentation and operating information.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.