Prerequisite Environmental Tobacco Smoke Control

Prevent smoke and electronic-smoking emissions from entering project spaces using the building-wide or project/HVAC-zone option.1

Points
Required
Applies to
ID+CBD+C
Other versions
v4
VERTIQ reference ID
EQp2

Reviewed · Spot an error? Report it

Points

Required prerequisite; 0 points. Select and document the applicable option.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: No-smoking policy, occupant communication and signage/enforcement provisions.
  • Preparation checklist: Building/project smoking-zone and HVAC/common-area map, plus exterior setback or migration-prevention evidence for the selected option.
  • Preparation checklist: For Option 2, a letter signed by the project owner attesting to the no-smoking policy and enforcement, plus mechanical plans or drawings showing smoking is prohibited in all areas on the project's HVAC system.
  • Preparation checklist: For Option 1 where local code sets the distance instead of 25 ft, a copy of the local code (translated into English, relevant sections highlighted) and a narrative of the code restrictions used.

Worked example

Assume the tenant selects Option 2 in a mixed-tenant building. Map the common areas and shared HVAC zone, prohibit smoking throughout those areas, and verify separation from any permitted smoking elsewhere. A lease clause covering only the suite is insufficient if the shared HVAC/common areas remain smoking areas.1

Requirements

Smoking includes tobacco, cannabis and controlled-substance combustion and emissions from electronic smoking devices.1

Option 1 locates the project in a building prohibiting smoking inside. Outside smoking is limited to designated areas at least 25 ft (7.5 m), or the maximum extent allowed by local codes, from entries, outdoor-air intakes and operable windows. Communicate the policy and provide enforcement provisions or signage.1

Option 2 prohibits smoking in project spaces, all common areas used by occupants and all areas served by the same HVAC system. If other building areas permit smoking, prevent ETS migration by mechanical or natural ventilation. Communicate the project policy and provide enforcement provisions or signage.1

FAQ

Are electronic smoking devices included?

Yes. The prerequisite definition includes their emissions.1

Does Option 2 prohibit smoking only inside the tenant suite?

No. It includes the common areas used by project occupants and areas served by the same HVAC system.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 Interior Design and Construction GuideNovember 2025 · Environmental Tobacco Smoke Control prerequisite, printed/PDF pp. 142-145; ID+C scorecard printed/PDF pp. 5-6