Prerequisite Fundamental Commissioning and Verification
Commission the fit-out energy, water and indoor-environmental-quality systems and coordinate affected base-building systems. Establish the owner requirements, design basis, verification process and operating information early.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; 0 points. Commissioning completion is a documented process rather than a percentage score.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: OPR, BOD, commissioning scope/plan, authority qualifications and design-review records.
- Preparation checklist: Construction checklists, functional tests, issues log, final report and current facilities/O&M plan.
Worked example
Assume a fit-out relocates air terminals and lighting controls but leaves an existing chiller unchanged. List the modified terminals and controls in the commissioning scope, verify their sequences and tests, and coordinate interfaces with the base-building operator. Record deficiencies and close them or identify outstanding issues in the final report; an untouched chiller does not justify omitting the modified tenant systems.1
Requirements
Follow ASHRAE Guideline 0-2013 and Guideline 1.1-2007 as applicable. Develop the owner project requirements (OPR) and basis of design (BOD). The commissioning authority reviews the OPR, BOD and project design; develops and implements the commissioning plan; confirms commissioning requirements are in the construction documents; develops construction checklists and a system test procedure; verifies test execution; maintains an issues and benefits log; prepares a final report; and reports findings directly to the owner throughout the process. Include enclosure requirements in the OPR/BOD and design review.1
Engage a commissioning authority by the end of design development. The authority needs documented experience on at least two similar projects from early design through at least 10 months of occupancy. The authority may be a qualified employee of the owner, an independent consultant, an employee of the design or construction firm who is not part of the project team, or a disinterested subcontractor of the design or construction team. For projects smaller than 20,000 square feet (1,860 square meters), a qualified member of the design or construction team may serve. In all cases the authority reports directly to the owner.1
Prepare current facilities requirements and an operations and maintenance plan. Include all fit-out systems and base-building items modified or relocated by the work, and coordinate sequences of operations, schedules, equipment setpoints and outside air requirements for tenant equipment and spaces with base building requirements.1
FAQ
Must the authority always be an outside company?
No. The Guide allows several qualified organizational arrangements, subject to its experience and independence conditions.1
Does fit-out commissioning stop at the lease line?
No. Include base-building items modified or relocated by the project and coordinate the systems that serve the fit-out.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.