Credit Advanced Energy Metering
Meter the tenant space under one of two ID+C options: basic whole-tenant energy reporting or advanced tenant and significant-end-use metering.1
Reviewed · Spot an error? Report it
Points
| Points | Requirement |
|---|---|
| 1 | Option 1 |
| 2 | Option 2 |
These are alternative options, with a 2-point maximum.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Tenant energy-source and end-use schedule, meter diagram and annual end-use calculation.
- Preparation checklist: Energy data sharing commitment for either option; for Option 1, tracking records; for Option 2, list of tenant-level advanced meters with metered source or end use and meter/BMS details, manufacturer specifications and interval/remote-access/storage/reporting records.
Worked example
Assume annual tenant energy is 1,000,000 kWh equivalent, and one end use consumes 120,000 kWh equivalent. Share = 120,000 / 1,000,000 x 100 = 12%, so that end use needs advanced metering under Option 2. A 90,000 kWh end use is 9% and does not independently trigger the 10% threshold. All total energy sources and the other advanced-meter requirements still apply.1
Requirements
Option 1 requires new or existing tenant-level meters representing total tenant-space energy use, monthly tracking and a five-year commitment to share the specified energy and electrical-demand data beginning at acceptance of certification, until the term ends or ownership/lessee changes. It does not require tenant-level metering of base building service water heating, locally generated energy dedicated to the project space, or shared air-handling or DX units that also serve areas outside the project; components exclusively serving the project space remain in the tenant total.12
Option 2 requires permanent advanced meters for all tenant energy sources and individual end uses representing at least 10% of total annual tenant energy. Collect data at intervals of one hour or less with remote access, electricity demand and appropriate power-factor data, storage for at least 18 months, and the required reporting capability. For shared air-handling units or shared renewable systems representing more than 10% of building energy, document that the building complies with the LEED BD+C Advanced Energy Metering requirements.12
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 Interior Design and Construction GuideNovember 2025 · Advanced Energy Metering, printed/PDF pp. 81-81; ID+C scorecard printed/PDF pp. 5-6
- LEED v4 Reference Guide for Interior Design and Construction AddendaCumulative through February 20, 2026 · EA Credit Advanced Energy Metering rows, addenda printed pp.12, 20 and 24
Maintained by VERTIQ, LEED software for consultants.