Credit Advanced Energy Metering

Collect remotely accessible hourly energy data with sufficient retention and end-use coverage.1

Points
1 point
Applies to
BD+CID+C
Other versions
v4
VERTIQ reference ID
EAc3

Reviewed · Spot an error? Report it

Points

1 point.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Energy end-use breakdown
  • List of all advanced meters with metered energy source or end use and meter/BMS details
  • Data retention/remote-access configuration
  • Core-and-Shell future-tenant meter plan where applicable
  • Single line diagrams and panel schedules showing all meters

Worked example

Assume a non-Core-and-Shell building uses 1,000,000 kWh-equivalent annually and a lighting end use is 120,000 kWh. Its 12% share exceeds the 10% threshold, so that end use requires advanced metering in addition to the whole-building sources.1

Requirements

For adaptations other than Core and Shell, install advanced meters for every whole-building energy source and individual end uses representing at least 10% of total annual building consumption. Record at intervals of one hour or less; transmit remotely and retain at least 36 months. Electricity meters record consumption and demand, and the system reports hourly through annual use.1

Core and Shell uses a separate scope: meter future tenant spaces for all systems dedicated to those spaces, with enough meters to capture total tenant energy use and at least one meter per energy source per floor. All energy sources used by a tenant need advanced metering, including electricity, natural gas, chilled water and heating hot water; service hot water may be excluded. Install advanced metering for all base-building energy sources with the specified recording, retention, access and reporting features.21

FAQ

Does a monthly utility bill meet this credit?

No. Advanced meters require intervals of one hour or less and the stated access, retention and reporting features.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 81-82
  2. LEED v4 BD+C Reference Guide AddendaCumulative table, February 20, 2026 · EA Credit Advanced Energy Metering, Further Explanation, Rating System Variations, Core and Shell, post date 4/14/2017, addenda PDF p. 43

Maintained by VERTIQ, LEED software for consultants.