Credit Construction and Demolition Waste Management

Develop a construction and demolition waste management plan, then earn points through diversion, waste prevention or both.1

Points
See below
Applies to
BD+CID+C
Other versions
v4
VERTIQ reference ID
MRc5

Reviewed · Spot an error? Report it

Points

1-2 points, maximum 2. Option 1 earns 1 point and Option 2 earns 2.1

The October 2026 guidance's Table 1 identifies one extra exemplary performance point for verified recycling rates in v4.1. It is separate from the base points, and third-party verification is not a condition of the base facility-average route.2

The Guide's exemplary performance criteria are achieving both options, or diverting 50% or more of all waste using certified recycling facilities for all commingled waste.3

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Construction and demolition waste management plan
  • Construction and demolition waste calculator showing total and diverted waste, with recycling rates for commingled facilities
  • Final waste report with demolition and new-construction waste tracked separately
  • Hauler weight tickets and receiving-facility receipts
  • Facility annual or monthly average recycling report matching each delivery date, with ADC treatment
  • Scale tickets or documented volume-to-weight conversion records, not visual estimates
  • Waste prevention narrative and total waste per area calculation, if pursuing Option 2
  • International projects: justification narrative and documentation that waste-to-energy facilities meet the EN standards, if used

Worked example

Assume a weight-based Option 1 report has 100 metric tonnes of included waste: 30 tonnes source-separated recycling, 50 tonnes commingled at a documented 60% facility recycling rate, and 20 tonnes disposal. Diversion = 30 + 50 x 0.60 = 60 tonnes; 60/100 x 100 = 60%, meeting the 1-point threshold if the plan and remaining requirements are satisfied. This does not establish the waste prevention option.1

Requirements

All BD+C adaptations, including Healthcare, use this credit. Develop and implement a construction and demolition waste management plan: identify source reduction strategies, target materials, diversion strategies, destinations and expected diversion rates. Provide a final report of all waste generated, with disposal and diversion rates. Use weight or volume consistently. Exclude excavated soil and land-clearing debris, treat alternative daily cover (ADC) as waste, and apply the facility-average recycling rate to commingled loads.1

Option 1 diverts at least 50% of total construction and demolition materials for 1 point. Option 2, for 2 points, diverts at least 50% of demolition waste, if any, and generates less than 10 lb/ft2 (50 kg/m2) from new construction, excluding hazardous materials and land-clearing debris. Track demolition and new-construction waste separately.1

For projects registered on or after November 9, 2020, the October 2026 supplemental guidance requires matching load-receipt dates and tickets to the facility's annual or monthly average rate. Its project-specific commingled-load route applies to v4 only, not v4.1. Use measured quantities: scale weights or acceptable volume-to-weight conversions. Visual estimates are not an accepted measurement method. Hazardous waste, excavated soil, land-clearing debris and landscaping materials are excluded from the diversion calculation. This supplement does not replace the rating requirements or GBCI review.2

The BD+C v4.1 Guide permits a conditional waste-to-energy route for international projects that cannot meet diversion requirements through reuse and recycling. Demonstrate that those strategies were exhausted. The facility must follow European Commission Directives 2008/98/EC and 2000/76/EC and meet applicable CEN EN 303 standards. Qualifying wood-derived biomass fuel is a separate diversion category for U.S. and international projects.34

Table 3 of the October 2026 supplement agrees: international v4.1 waste-to-energy is allowed and U.S. v4.1 waste-to-energy is not. Its p. 4 definition still reads v4 only. The supplement states that it does not replace official USGBC guidance, so follow the Guide's conditional route. Ordinary incineration is not diversion.23

FAQ

Is there a separate Healthcare version of this credit?

No. Healthcare uses this credit at 1-2 points, like the other BD+C adaptations.1

Can I mix weight and volume totals?

No. The reported calculation must use one consistent measurement basis.1

Does alternative daily cover count as recycling?

No. Include it as waste rather than diversion.1

Can international v4.1 waste-to-energy be counted?

It may qualify under the published international alternative compliance path if reuse and recycling cannot meet the diversion requirement and those strategies were exhausted. The facility must follow Directives 2008/98/EC and 2000/76/EC and applicable CEN EN 303 standards. Provide the justification narrative and facility documentation.34

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Construction and Demolition Waste Management, printed/PDF pp. 109-110
  2. USGBC Commingled (Mixed) Construction and Demolition Recycling Rate ReportingOctober 2026 · p. 1 applicability note and Table 1; p. 2 Table 2; p. 3 Table 3; p. 4 key terms
  3. LEED v4.1 BD+C GuideNovember 2025 · Construction and Demolition Waste Management, printed/PDF pp. 218-222: Further Explanation, International Tips, Required Documentation, Exemplary Performance
  4. USGBC Reference Guide Correction 100002469November 9, 2020; live entry checked October 28, 2026 · BD+C v4.1, Construction and Demolition Waste Management; International Tips and Required Documentation