Credit Daylight
Evaluate daylight with one of the annual simulation, point-in-time simulation or measurement routes and control glare.1
Reviewed · Spot an error? Report it
Points
Annual simulation awards 1/2/3 at average sDA 40/55/75% for general BD+C; a general project at 2 points earns 1 additional point if each regularly occupied space reaches sDA300/50% of at least 55%. Healthcare has a 2-point maximum. Other routes have different area/timing thresholds.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Daylight model/report with weather, grid and obstruction assumptions
- Regularly occupied-area schedule
- Glare-control design
- Field measurement locations, dates and readings if selected
Worked example
Assume a compliant NC annual simulation reports average sDA300/50% of 60% across the applicable area. It reaches the 55% row for 2 points, not the 75% row; a third point would need each regularly occupied space at sDA300/50% of at least 55%. Review ASE spaces above 10% and glare-control requirements separately.1
Requirements
Provide manual or automatic-with-manual-override glare control, with the stated Core and Shell tenant-space exception. Annual simulation uses sDA and ASE with compliant grid, weather and modeling assumptions. The illuminance simulation and field measurement routes use their own area thresholds, timing and grid rules. Healthcare uses its defined perimeter-space scope and point cap; do not transfer general whole-building denominators to it.1
FAQ
Can an annual sDA result be scored against the illuminance table?
No. Each option uses its own metric, thresholds and documentation.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.