Credit Indoor Air Quality Assessment

Use a complete flush-out or the permitted air-testing path after construction and cleaning.1

Points
See below
Applies to
BD+CID+C
Other versions
v4
VERTIQ reference ID
EQc4

Reviewed · Spot an error? Report it

Points

Flush-out earns 1 point. Air testing earns 1 point for each compliant path, up to 2.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Flush-out outdoor-air flow, duration and environmental logs
  • Final finish/furnishing completion records
  • IAQ testing report and sampling plan if testing, with the ISO/IEC 17025 certificate and accredited scope where a laboratory is used
  • Investigation/correction/retest records where needed

Worked example

Assume the flush-out floor area is 10,000 ft2. The total outdoor-air target is 10,000 x 14,000 = 140,000,000 ft3. At a verified constant outdoor-air flow of 20,000 cfm this is 7,000 minutes, or 116.67 hours, while required temperature/humidity conditions are maintained. This is not an air-testing result.1

Requirements

Complete finishes/furnishings and major VOC punch-list work before the selected assessment. Flush-out supplies 14,000 ft3 of outdoor air per ft2, within the stated temperature/humidity conditions; early occupancy requires 3,500 ft3/ft2 first and continued controlled ventilation. The alternative testing route uses particulate/inorganic and/or VOC paths with approved methods and limits; laboratories that conduct the tests must be ISO/IEC 17025 accredited for the methods they use. The flush-out and air-testing options cannot be combined. Retail has a limited post-occupancy testing allowance.1

FAQ

Can a partial flush-out and one passing sample combine for two points?

No. The two options cannot be combined, and each testing path has its own complete contaminant and method requirements.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 126-128

Maintained by VERTIQ, LEED software for consultants.