Prerequisite Minimum Energy Performance
Demonstrate compliance with ASHRAE 90.1-2016 with errata or a USGBC-approved equivalent, using an allowed compliance route.1
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points. Credit points under Optimize Energy Performance are a separate calculation.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Energy compliance report naming the standard and route
- Baseline/proposed simulation output and PCI/PCIt worksheet
- Mandatory-provision compliance checklist
- ASHRAE 90.1-2016 compliance forms or COMcheck report confirming system-by-system compliance with all mandatory and prescriptive provisions, with supporting construction drawings, where the prescriptive route is used
- Renewable-energy boundary and ownership documentation where used
Worked example
Assume a valid Appendix G cost calculation yields PCI = 0.58 and PCIt = 0.60. Since 0.58 <= 0.60, this numeric comparison passes; improvement = (1 - 0.58/0.60) x 100 = 3.3333%. It does not independently prove mandatory-provision compliance, model validity or the applicable adaptation path.1
Requirements
Meet the applicable mandatory provisions and one of the prescriptive, Energy Cost Budget or Appendix G routes in Section 4.2.1.1. Under Appendix G, document PCI, PCIt and percentage improvement using cost or greenhouse-gas metrics, with PCI no greater than PCIt. The prerequisite includes a specific modeling exception to mandatory provisions and allows compliant exceptional calculations; these are documented paths, not a blanket exemption.1
Only on-site or on-campus renewables meeting the stated ASHRAE requirement may contribute to minimum compliance. Keep the selected standard, errata and any approved equivalent path explicit. Data Centers appear on the applicability list but not in the requirements heading, so use the Data Centers guidance under this prerequisite for modeling and calculator requirements.31
FAQ
Can purchased off-site renewable energy close a prerequisite shortfall?
The cited prerequisite permits only qualifying on-site or on-campus renewables for minimum performance.1
Can I substitute a different BPF table without approval?
Use the factors required by the selected standard and approved path.3
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 69
- LEED v4.1 BD+C Addenda Table, first editionNovember 3, 2025 cumulative table · EA prerequisite Minimum Energy Performance, Required Documentation, Addenda PDF p. 50 (Guide p. 134)
- LEED v4.1 BD+C GuideNovember 2025 · EA Prerequisite Minimum Energy Performance, Equation 2, p. 108; Rating System Variations, Data Centers, pp. 124-125