IPp1 Climate Resilience Assessment

Assess current and future natural hazards and identify at least two priority hazards with design responses considered.1

Points
Required
Applies to
ID+CBD+CO+M

Reviewed · Spot an error? Report it

Points

Required prerequisite; no points. A hazard list without the requested assessment and priority-strategy discussion is incomplete.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation: Scenario, service-life and hazard-assessment record
  • Preparation: Exposure/vulnerability/risk findings and references
  • Preparation: At least two priority-hazard strategy narratives

Worked example

Assume the assessment identifies five applicable hazards and selects extreme heat and smoke as the two priorities. Five hazards are assessed, while two priorities meet the minimum count. The selection still requires scenario, risk, vulnerability and strategy documentation.1

Requirements

Evaluate site-specific current and projected hazards affecting the site or building function, including relevant heat, cold, flood, drought, storm, smoke, fire and other hazards. For each applicable hazard identify the IPCC scenario/shared socioeconomic pathway, projected service life, hazard and risk levels, exposure, sensitivity, adaptive capacity, vulnerability, functional impacts and construction-period impacts.1

Identify at least two priority hazards for proposed design strategies and describe how project-specific strategies were considered. Use findings to inform planning, design, operations and maintenance where possible.1

FAQ

Must the assessment choose a single priority hazard?

No. It must identify at least two.1

Does the prerequisite consider construction as well as operations?

Yes. Potential site impacts during construction are among the requested assessment items.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 ID+C Rating SystemJuly 2026 · IPp1; printed pp. 5-6, PDF pp. 10-11; scorecard printed pp. 1-2, PDF pp. 6-7

Maintained by VERTIQ, LEED software for consultants.