EAc5 Grid Interactive
Reduce peak thermal loads, add controlled storage, participate in demand response or provide qualifying demand management and power resilience.1
Reviewed · Spot an error? Report it
Points
Maximum 3 points. Peak thermal-load paths earn up to 3; storage earns 1-2; demand response, automated demand management and power resilience each earn 1, subject to the combined cap.1
Exemplary performance: achieving all four options earns 1 exemplary performance point, claimed under Project Priorities (EP13).2
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation: Selected-option drawings, calculations and test reports
- Preparation: Storage capacity, peak-demand basis and automatic-control sequence
- Preparation: DR contract, load-shed plan or islanded critical-load analysis as applicable
- Preparation: Evidence that storage, demand-response, demand-side management and power-resilience controls are in the CxP scope and in the systems manual or CFR and O&M plan
Worked example
Assume peak tenant electrical demand is 100 kW and qualifying controlled electrical storage is 40 kWh. Capacity ratio = 40 / 100 = 0.4 kWh/kW, meeting the 2-point electrical-storage threshold. A separate qualifying demand-response contract adds 1, bringing the total to 3.1
Requirements
Option 1 awards one point each for qualifying energy/heat recovery, low envelope conductance and air-leakage performance. Apply the distinct initial-build-out and existing-building criteria, test conditions and permitted exclusions. Each requirement may be documented at the building level or for the project only.1
Option 2 provides controlled electrical and/or thermal storage at the Table 2 demand-relative ratios. Controls must shift storage and discharge toward lower-demand or lower-carbon periods. Option 3 requires at least a one-year demand-response contract with intent to renew.1
Option 4 provides automated controls across at least two listed systems at their coverage thresholds, or a building-automation plan shedding at least 10% of peak electric demand for at least one hour in winter and summer. Combustion-based on-site electricity cannot meet these demand-management criteria. Option 5 supplies critical loads independently for at least three days using on-site renewables and storage.1
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v5 ID+C Rating SystemJuly 2026 · EAc5; printed pp. 61-64, PDF pp. 66-69; scorecard printed pp. 1-2, PDF pp. 6-7
- USGBC LEED credit library: Grid Interactive: Exemplary Performance (EP13)Published Apr 22, 2025; retrieved November 8, 2026 · EP13 requirements
Maintained by VERTIQ, LEED software for consultants.