EAc6 Grid Interactive
Use storage, demand response, automated load management, or resilient renewable/storage systems to respond to grid conditions.1
Reviewed · Spot an error? Report it
Points
NC and Core and Shell: maximum 2 points. Storage earns 1/2 at electric storage ratios 0.2/0.4 kWh per kW peak demand, or thermal ratios 1.0/2.0 kWh per kW coincident thermal peak. DR, automated management, and power resilience each earn 1 within the cap.1
Exemplary performance: achieving all four options earns 1 exemplary performance point, claimed under Project Priorities (EP13).2
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Grid-interactive evaluation and control sequence
- Interval meter/external-signal equipment schedule
- Peak demand and storage-capacity calculation
- Demand-response agreement or automated shed plan, if used
- Critical-load and three-day islanding model for the resilience option
- Commissioning scope and systems manual (or Current Facilities Requirements and O&M plan) covering the grid-interactive technology and controls
- Core and Shell tenant lease language covering automatic demand response controls, for Option 3
Worked example
Assume a 1,000 kW peak electrical demand and 400 kWh qualifying controlled storage. Ratio = 400/1,000 = 0.4 kWh/kW, reaching the 2-point electrical storage band. This energy-to-power ratio does not prove three-day critical-load resilience.1
Requirements
Evaluate the current/forecast grid context, project location/type, and ownership structure. Provide interval meters and external-signal-capable equipment. Storage requires automatic charging/discharging management; DR requires a qualified program contract for at least one year with multiyear-renewal intent. Automated management uses eligible system controls or a building-wide shed plan. On-site generation and fuel combustion cannot satisfy the demand-side-management criteria. Power resilience requires islanded critical-load operation using on-site renewables and storage for at least three days.1
FAQ
Does a generator count as demand reduction?
The demand-side-management criteria expressly exclude on-site electricity generation and fuel combustion.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v5 BD+C Rating SystemJuly 2026 · EAc6, printed pp. 120-122
- USGBC LEED credit library: Grid Interactive: Exemplary Performance (EP13)Published Apr 22, 2025; retrieved November 8, 2026 · EP13 requirements