EAc1 Electrification

Reduce dependence on on-site combustion using efficient electrified equipment. NC and Core and Shell have different achievement paths, and Platinum requires the maximum electrification achievement for the applicable system.1

Points
See below
Applies to
BD+CID+C

Reviewed · Spot an error? Report it

Points

NC: 1-5 points; Option 1 earns 5. Option 2 has space heating 2, service water heating 1, and cooking/other process 1, capped at 4. C&S: 1-4 points with installed-system and readiness paths as applicable. Platinum requires 5 points for NC or 4 for C&S.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Mechanical equipment schedule with fuels, capacities, and COP ratings
  • Heating and service-water-heating weighted-COP calculation
  • Mechanical and electrical drawings showing electrified systems or readiness
  • Emergency-system description with estimated annual combustion run-time, and for Option 2, sequence of operations with evidence that electric equipment meets loads above 20°F
  • District-energy compliance documentation, if applicable
  • Core and Shell tenant electrification guidelines, if applicable
  • Core and Shell: code excerpts or tenant construction drawings confirming a 1.8 weighted-average COP for excluded future equipment, or the Path 3 calculation of installed capacity as a percentage of peak combined heating and service water heating load, as applicable

Worked example

Assume an NC Option 1 project with no non-emergency combustion, heating/SWH systems of equal weighting and COPs 2.0 and 2.4 under the permitted rating method. Weighted COP = (2.0 + 2.4)/2 = 2.2, above 1.8. This illustrates only the efficiency check; the complete equipment inventory and operating design must also demonstrate the combustion restriction and other requirements.1

Requirements

For NC, Option 1 requires operation from startup without on-site combustion other than emergency support systems and a combined weighted-average heating and service-water-heating COP of at least 1.8, subject to the stated exclusions. Option 2 allows qualifying low-temperature combustion and separate space-heating, water-heating, and cooking/process paths.1

For Core and Shell, choose one Option 1 installed-system path (Path 1, Path 2, or Path 3) and/or add the Option 2 readiness point, within the credit cap. Readiness includes reserved equipment space, piping/chases, electrical capacity where in scope, and tenant guidance. Low temperatures are below 20°F; the Rating System prints -6.5°C for SI. Follow the specified efficiency-rating conditions and district-energy provisions; fossil-fuel cells are ineligible.1

FAQ

Is electric resistance equipment enough to satisfy every path?

No. The applicable path also imposes efficiency conditions, including the 1.8 weighted-COP requirement where specified.1

Does emergency backup combustion automatically disqualify the no-combustion path?

The stated path permits emergency support systems. Document their scope and distinguish them from normal building heating or process equipment.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · EAc1, printed pp. 86-91

Maintained by VERTIQ, LEED software for consultants.