Prerequisite Construction and Demolition Waste Management Planning

Plan diversion for at least five material categories and report final disposal and diversion.1

Points
Required
Applies to
ID+CBD+C
VERTIQ reference ID
MRp2

Reviewed · Spot an error? Report it

Points

Required prerequisite, with no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preparation checklist: Dated waste-management plan with five targets, destinations and handling strategy.
  • Preparation checklist: Final stream report, tickets and destination/recovery evidence.

Worked example

Assume the plan targets concrete, metal, wood, cardboard and gypsum. The five-category count is met. If 100 tonnes is generated and 60 diverted, the final report would show 60% diversion; the prerequisite still needs the implemented plan and complete major-stream report.1

Requirements

Develop and implement a plan identifying at least five structural/nonstructural materials targeted for diversion and their approximate share of project waste. State separation or commingling, destinations and recovery-facility processing. Provide a final report for major waste streams and their disposal/diversion rates.1

Count alternative daily cover as disposal, not diversion. Land-clearing debris does not contribute as C&D waste.1

FAQ

Does a five-category plan automatically earn the waste credit?

No. The prerequisite planning requirements are separate from the credit diversion or waste-generation thresholds.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.