Prerequisite Construction and Demolition Waste Management Planning
Plan construction-waste diversion and provide a final report of actual waste outcomes.1
- Points
- Required
- Applies to
- BD+CID+C
- VERTIQ reference ID
- MRp2
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points. The planning requirement is separate from earning Construction and Demolition Waste Management diversion points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Construction waste management plan
- Target-material and destination schedule
- Recycler/hauler agreements
- Final waste/diversion report
Worked example
Assume five targeted materials account for estimated shares of 25%, 20%, 15%, 10% and 5% of waste. Together they represent 75%. That is a planning estimate, not a measured 75% diversion achievement.1
Requirements
Identify at least five structural/nonstructural materials targeted for diversion and estimate their share of overall waste. Describe separation/commingling, destinations and processing. Provide the final major-stream report with disposal/diversion rates. Alternative daily cover is waste; land-clearing debris cannot contribute to construction-waste diversion.1
FAQ
Does naming five target materials establish actual diversion points?
No. The prerequisite plan and final outcomes are distinct from the credit's measured diversion and stream thresholds.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.