Credit Water Metering
Submeter at least two qualifying water subsystems with their required coverage.1
- Points
- 1 point
- Applies to
- BD+C
- Other versions
- v4.1
- VERTIQ reference ID
- WEc4
Reviewed · Spot an error? Report it
Points
1 point.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Water submeter diagram
- Subsystem coverage takeoff
- Meter specifications
- Boiler/process and Healthcare equipment schedules where applicable
- Water metering strategy narrative
Worked example
Assume indoor-fixture metering covers 90 of 100 fixtures and irrigation metering serves 900 of 1,000 m2 irrigated landscape. Both coverages equal 90%, exceeding 80%, and together provide two qualifying subsystems if the meter boundaries are correct.1
Requirements
Choose at least two applicable subsystems from irrigation, indoor fixtures, domestic hot water, qualifying boilers, reclaimed water and other process water. Flush fixtures and flow fixtures that are submetered separately count as two subsystems. The categories have distinct coverage thresholds and sizing rules. Indoor fixtures and several other subsystems require at least 80% coverage. Healthcare must additionally install meters in any five of the listed Healthcare subsystems.21
FAQ
Does a whole-building meter count as two subsystems?
No. This credit requires separate qualifying subsystem coverage beyond the building-level metering prerequisite.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 BD+C Rating SystemUpdated July 25, 2019 · Water Metering, printed/PDF pp. 61-62
- LEED v4 BD+C Reference Guide AddendaCumulative table, February 20, 2026 · WE Credit Water Metering, Step-by-Step Guidance, Step 1, post date 1/10/2020, addenda PDF p. 32
Maintained by VERTIQ, LEED software for consultants.