Credit Integrative Process
Use early energy and water analysis to inform coordinated design decisions.1
Reviewed · Spot an error? Report it
Points
1 point.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Simple-box energy study with tested alternatives
- Integrative Process worksheet (energy and water analysis tabs) and preliminary water balance
- OPR and BOD
- Design-meeting decision log
Worked example
Assume an early water balance estimates 1,000 m3/year demand and 300 m3/year of usable captured water. The potential offset is 300 / 1,000 x 100 = 30%. This is a discovery-stage design comparison, not a separate water-credit award.1
Requirements
Begin in pre-design and continue through design. Complete a preliminary simple-box energy analysis before schematic design ends, testing at least two strategies for each listed energy topic. Complete the preliminary water budget before schematic design ends, assess water demands and potential supplies, and analyze at least one on-site nonpotable supply against at least two of the listed demand components. Document how findings inform the OPR, BOD and design.12
FAQ
Can the study be written only after design is complete?
The required analysis is intended to guide pre-design and schematic decisions; a retrospective description does not replace that timing.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4 BD+C Rating SystemUpdated July 25, 2019 · Integrative Process, printed/PDF pp. 9-10
- LEED v4 Reference Guide for Building Design and Constructionv4 Reference Guide · Integrative Process, Step-by-Step Guidance, Step 5
Maintained by VERTIQ, LEED software for consultants.