Credit Integrative Process
Use early cross-disciplinary analysis to influence the fit-out design, or locate in a LEED-certified building. The Guide contains a one-versus-two-point inconsistency that needs confirmation before claiming both options.1
Reviewed · Spot an error? Report it
Points
The requirements identify two options at 1 point each and a 1-2-point header; the scorecard lists 1 point, but its category totals reach the printed 110 only when this credit counts 2, so both options can be combined for up to 2 points.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation checklist: Two selected issue-area analyses, timing records, design goals and links to OPR/BOD and design changes.
- Preparation checklist: Dated signed Project Team Letter and stakeholder distribution record; LEED building certification if Option 2 is pursued.
Worked example
Assume the team selects energy and water during predesign, completes both preliminary studies before schematic design ends, changes lighting and fixture selections using the results, and documents the influence in the signed team letter. This is a complete Option 1 procedure supporting its stated 1 point; it does not assume a second point from Option 2.1
Requirements
Option 1 starts in predesign and continues through design. Choose two issue areas from energy, water, resilience, social equity and health/well-being, and follow the applicable analysis. For energy or water, perform the preliminary analysis before completion of schematic design; set the energy target no later than schematic design. Show how findings informed the OPR, BOD and design/construction documents.1
Provide a dated Project Team Letter on the Integrative Process Facilitator letterhead. Summarize the process, each issue analysis and design influence, obtain principal team-member signatures, and explain distribution to key stakeholders.1
Option 2 selects a LEED-certified building. The requirements join the two one-point options with AND/OR, but the scorecard lists a one-point credit.1
FAQ
Must Option 1 always analyze energy and water?
No. The Guide requires two selected issue areas from the five listed areas.1
Can the scorecard and requirements both establish the cap?
They differ. The scorecard says one, while the requirements describe up to two. The applicable cap needs official confirmation.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v4.1 Interior Design and Construction GuideNovember 2025 · Integrative Process, printed/PDF pp. 9-13; ID+C scorecard printed/PDF pp. 5-6