Prerequisite Building-Level Energy Metering

Track all relevant whole-building energy sources and commit to share consumption data.1

Points
Required
Applies to
BD+C
Other versions
v4
VERTIQ reference ID
EAp3

Reviewed · Spot an error? Report it

Points

Required prerequisite; no points.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Energy service/meter diagram
  • Meter inventory and data-aggregation method
  • Data sharing confirmation
  • Monthly energy reporting schedule
  • Meter declaration

Worked example

Assume two electric service meters show 12,000 and 8,000 kWh in the same month. Whole-building electricity is 20,000 kWh. Report a separate gas or district-energy source as well; the electric total does not represent all-source coverage.1

Requirements

Install new or use existing meters, or submeters that can be aggregated, to capture total building energy by source, including delivered district energy where applicable. Track at least monthly and share consumption plus metered electrical demand for five years. Core and Shell uses base-building scope and starts its sharing period at certification acceptance or typical occupancy, whichever is first; the general route starts at certification acceptance.1

FAQ

Can utility-owned meters qualify?

Yes, if they capture the required building-level resource use.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v4.1 BD+C Rating SystemFebruary 2025 download; cover dated July 28, 2023 · Printed and PDF pp. 70

Maintained by VERTIQ, LEED software for consultants.