Rooms are grouped into thermal blocks you can edit, HVAC is built in the rooms your mechanical drawings show, and Appendix G baselines run on more buildings.

This release changes how VERTIQ builds the energy model from your drawings. Before you start:

  • Energy results for projects with HVAC read from drawings change once on the next run, because each room now gets the equipment the drawings link to it.
  • Appendix G baselines with hot-water VAV reheat boxes are sized differently, so percent savings on those projects may change.

New

  • Thermal blocks you can edit. Energy models group rooms into thermal blocks using their drawing HVAC links, floor, exposure, loads and schedules. In the Zones tab you can preview a grouping, keep your own blocks, or send rooms back to automatic grouping. The next energy run uses your zoning. A block you draw across designed mechanical zones is noted for review.
  • Areas outside your contract. You can keep a conditioned buffer along drawing areas marked not in contract. Model review and Appendix G reports show the buffer area and its electricity, and savings count the same buffer energy in both totals.
  • Rooms from enlarged plans. A registered enlarged plan can restore a space missed on the floor plan when a room confirms its boundary, and its room names are read.

Improved

  • HVAC from your drawings. Every room link read from the mechanical schedules and plans now reaches the energy model, so heat pumps, fan coils and ERVs are built in the rooms they serve. Water source heat pump schedules are modeled on a heat pump loop with the drawn cooling tower and boiler.
  • Outdoor air units. DOAS and ERV units supply outdoor air only. When two units serve one room, both are installed and the room's outdoor air is split between them. Heat recovery and supply temperature follow the equipment schedule, and when the schedule does not state them the applicable ASHRAE 90.1 minimum is used and shown for review. Water source outdoor air units are listed in the Review Queue and not yet modeled; in this release the zone equipment supplies their rooms' outdoor air.
  • Rooms without a linked unit. They get their own autosized unit of the design's most common type, or a terminal of the main air system, and the Review Queue says which default was used and why. A design with no heating or cooling equipment gets the ASHRAE 90.1 Appendix G baseline system type. Equipment that appears only on riser or control diagrams, with no schedule row, is listed for review instead of being modeled.
  • Equipment sized for the rooms it serves. A unit whose stated capacity covers several thermal blocks is sized per block instead of copying the full capacity into each one. An air system that also serves rooms with no drawn link is sized automatically, and the Review Queue shows when its size differs from the schedule by more than 20%.
  • Appendix G VAV reheat. On ASHRAE 90.1-2010, 2016 and 2019 baselines, hot-water VAV reheat boxes deliver the zone heating design airflow while reheating, keeping the 30% minimum and the design supply temperature difference. Baseline heating is no longer oversized to make up for boxes that could not meet their load. The result notes where this differs from the PNNL Appendix G guidance.
  • Appendix G windows (90.1-2016 and 2019). When one facade cannot hold its share of the baseline window area, the rest moves to the other facades in proportion to their free wall area. The building window ratio stays at the table value, and the result lists the area moved per facade for review. These baselines used to stop with an error.
  • Appendix G in climate zones 0A and 0B (90.1-2010). ASHRAE 90.1-2010 has no zone 0, so these baselines now use the zone 1A and 1B table rows, and the result names both zones. Later editions keep zone 0.
  • Fewer stopped energy runs. Duplicate room IDs, unreadable void covers, narrow slivers along contract boundaries and detached unconditioned structures no longer stop a run. Each is flagged for you to confirm. An unnamed space enclosed by rooms is modeled as indoor unconditioned space unless the drawing marks it open, and is flagged for review. Energy runs also queue and resume more reliably when the service is busy, and a model too large to simulate is reported with its size and a next step: group rooms into fewer thermal blocks in the Zones tab.
  • Daylight and passive survivability keep going. Daylight can use the building model and weather of the analysis when the energy simulation fails, and reports the energy failure separately. When passive survivability lacks run settings, the analysis names the Project Information fields to check and continues with the other results.

Fixed

  • Vector floor plans. Room outlines are traced across door thresholds, wall fill and thin double-line wall rings no longer count as floor area, diagonal walls keep their course through window openings, and crossed bay markings no longer create rooms without other floor evidence.
  • Windows and overhangs. Windows are placed on their finished walls, and clipped or unplaced openings are listed for review. Facades under an upper-floor overhang stay exposed so their windows can be placed.
  • Lab building use. Projects with "Lab" as the building use now use the Laboratory classification in the energy model.

Changed

  • Clearer scores. The Scorecard, Project Overview and credit panels label the combined total "Workspace score" and show the points you confirmed separately from calculated results. Results that meet a credit's criteria read "Criteria met", evidence you accept reads "Accepted", and printed reports label scores "Points".
  • Credit opportunities. The Compliance Optimization tab is now called Credit opportunities.
  • Thermal Comfort. The ASHRAE 55 compliance bar is removed. The unmet heating and cooling hour cards remain.
  • Shorter notices. Notices on the CFD, feasibility, credit input and evidence screens are shorter, and partial analysis emails point to the issues to review before you run again.