WEc2 Advanced Water Metering
Submeter at least two eligible water subsystems and use the readings to examine trends.1
- Points
- 1 point
- Applies to
- O+M
Reviewed · Spot an error? Report it
Points
1 point for meeting the subsystem, recording, analysis, and applicable calibration requirements.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Subsystem metering diagram and coverage calculations
- Weekly meter log and trend review
- Manufacturer calibration and maintenance records
Worked example
Assume meters cover 8,500 of 10,000 square feet of irrigated area and 90 of 100 indoor fixtures, with all remaining conditions met. Coverage is 85% and 90%, so these are two qualifying subsystems. Two meters on the same subsystem do not establish two subsystem categories.1
Requirements
Select at least two listed subsystems. Irrigation, indoor fixtures, domestic hot-water capacity, and other process-water uses generally have 80% coverage tests with different denominators. Cooling towers require replacement-water metering for all serving towers. Meter reclaimed water and its makeup supply so the reclaimed component is identifiable. Record every meter, including whole-building meters, at least weekly, analyze trends, and calibrate project-controlled meters on the manufacturer's interval.1
FAQ
Is the same 80% denominator used for every subsystem?
No. The source uses irrigated area, fixtures, heating capacity, or expected daily process use as appropriate. Cooling towers and reclaimed water have their own provisions.1
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v5 O+M Rating SystemJuly 2026 · WEc2, printed pp. 29-29 (PDF pp. 35-35); scorecard pp. 1-2
Maintained by VERTIQ, LEED software for consultants.