SSc2 Light Pollution and Bird Collision Reduction

Control night lighting or document qualifying bird-friendly glazing.1

Points
See below
Applies to
O+M

Reviewed · Spot an error? Report it

Points

1 point through either complete option. Interior lighting controls alone do not complete Option 1.1

Exemplary performance: achieving both Option 1 and Option 2 earns 1 exemplary performance point, claimed under Project Priorities (EP16).2

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Exterior fixture and cutoff schedule
  • Interior/exterior control settings and operating schedules
  • Glazing threat-factor evidence and elevation scope if selected

Worked example

Assume every exterior fixture above 1,000 lumens meets full cutoff, programmed nighttime interior lighting lasts 60 minutes, and nonessential exterior fixtures are off from midnight to 6 a.m. These conditions follow the three-part 1-point lighting route, with the source's full scope checked.1

Requirements

Option 1 combines full-cutoff exterior fixtures above 1,000 lumens, at least one listed interior-lighting control, and at least one exterior-lighting control. Examples of the listed alternatives include limiting programmed nighttime lighting to less than 90 minutes and turning off nonessential exterior lighting from midnight to 6 a.m. Option 2 requires glazing threat factor no greater than 30 in the stated zones: up to 50 feet above grade, up to 20 feet above green roofs, and glass guardrails/wind barriers at any height.1

FAQ

Does bird-friendly glass need treatment only below 50 feet?

The source also addresses glass above green roofs and glass guardrails/wind barriers at any height. Include all applicable zones.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 O+M Rating SystemJuly 2026 · SSc2, printed pp. 24-25 (PDF pp. 30-31); scorecard pp. 1-2
  2. USGBC LEED credit library: Light Pollution and Bird Collision Reduction: Exemplary Performance (EP16)Published Apr 22, 2025; retrieved November 8, 2026 · EP16 requirements

Maintained by VERTIQ, LEED software for consultants.