EAc7 Commissioning

Use completed retro-commissioning or an ongoing monitoring-based commissioning process.1

Points
See below
Applies to
O+M

Reviewed · Spot an error? Report it

Points

Up to 2 points: retro-commissioning earns 2; basic MBCx earns 1; enhanced MBCx earns 2. These paths are alternatives.1

Exemplary performance: achieving Option 1 and at least one of the two paths in Option 2 earns 1 exemplary performance point, claimed under Project Priorities (EP7).3

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • RCx provider qualifications, plan, measures, and final report
  • MBCx plan, EIS reports, corrective-action and training records
  • Updated CFR/O+M plan and continuation commitment
  • Enhanced MBCx provider contract or staff qualifications, and FDD training confirmation where applicable

Worked example

Assume an eligible third-party provider completes the full RCx process 18 months before the end of the reporting period, including verification and handoff. This is within the three-year window and follows the 2-point path; the date alone does not prove completion.1

Requirements

Retro-commissioning must be completed within three years before the reporting period ends, using an experienced third-party provider and the required planning, assessment, measures, verification, report, plan updates, and training. Basic MBCx needs its plan, EIS functionality, staff training, corrective actions, reporting, and a continuation plan of at least three years. Enhanced MBCx adds provider coordination, quarterly communication, enhanced EIS, applicable submetering, and capacity-triggered FDD. The addenda allow a shorter EIS operating record, at least three months, under stated conditions.21

FAQ

Must a new EIS already have operated for the full 12 months?

The February 2026 correction permits the summary to cover the EIS operating period, with at least three months, when it was not available at the start. Corrective action must begin during the reporting period.21

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 O+M Rating SystemJuly 2026 · EAc7, printed pp. 54-57 (PDF pp. 60-63); scorecard pp. 1-2
  2. LEED v5 O+M cumulative addendaJuly 31, 2026 · PDF p. 4, EAc7: November 2025 point correction and February 2026 RCx/EIS reporting provisions
  3. USGBC LEED credit library: Enhanced Commissioning: Exemplary Performance (EP7)Published Apr 22, 2025; retrieved November 8, 2026 · EP7 requirements

Maintained by VERTIQ, LEED software for consultants.