EAc7 Commissioning
Use completed retro-commissioning or an ongoing monitoring-based commissioning process.1
- Points
- See below
- Applies to
- O+M
Reviewed · Spot an error? Report it
Points
Up to 2 points: retro-commissioning earns 2; basic MBCx earns 1; enhanced MBCx earns 2. These paths are alternatives.1
Exemplary performance: achieving Option 1 and at least one of the two paths in Option 2 earns 1 exemplary performance point, claimed under Project Priorities (EP7).3
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- RCx provider qualifications, plan, measures, and final report
- MBCx plan, EIS reports, corrective-action and training records
- Updated CFR/O+M plan and continuation commitment
- Enhanced MBCx provider contract or staff qualifications, and FDD training confirmation where applicable
Worked example
Assume an eligible third-party provider completes the full RCx process 18 months before the end of the reporting period, including verification and handoff. This is within the three-year window and follows the 2-point path; the date alone does not prove completion.1
Requirements
Retro-commissioning must be completed within three years before the reporting period ends, using an experienced third-party provider and the required planning, assessment, measures, verification, report, plan updates, and training. Basic MBCx needs its plan, EIS functionality, staff training, corrective actions, reporting, and a continuation plan of at least three years. Enhanced MBCx adds provider coordination, quarterly communication, enhanced EIS, applicable submetering, and capacity-triggered FDD. The addenda allow a shorter EIS operating record, at least three months, under stated conditions.21
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.
- LEED v5 O+M Rating SystemJuly 2026 · EAc7, printed pp. 54-57 (PDF pp. 60-63); scorecard pp. 1-2
- LEED v5 O+M cumulative addendaJuly 31, 2026 · PDF p. 4, EAc7: November 2025 point correction and February 2026 RCx/EIS reporting provisions
- USGBC LEED credit library: Enhanced Commissioning: Exemplary Performance (EP7)Published Apr 22, 2025; retrieved November 8, 2026 · EP7 requirements
Maintained by VERTIQ, LEED software for consultants.