EAp3 Fundamental Commissioning
Commission the project systems and tenant/base-building interfaces against the owner's requirements.1
- Points
- Required
- Applies to
- ID+CBD+C
Reviewed · Spot an error? Report it
Points
Required prerequisite; no points. Enhanced commissioning is a separate credit.1
Documents to prepare
Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.
- Preparation: OPR, BOD and commissioning plan
- Preparation: CxP appointment, qualifications and review comments
- Preparation: Meeting records and contractor-documentation sampling record
- Preparation: Final or draft commissioning report, with a completion plan if draft
Worked example
Assume the completed contractor QA/QC set contains 80 records. A 10% sample is 8 records. Reviewing those eight addresses the sampling minimum only; it does not replace the OPR, BOD, meetings and applicable ASHRAE commissioning tasks.1
Requirements
Apply the ASHRAE 90.1 commissioning requirements to systems, controls and envelope within scope, including tenant/base-building interfaces. Use 2019 or later before January 1, 2028 registration and 2022 or later thereafter; Section 4.2.5.2 exceptions do not remove commissioning.1
By the end of design development designate a CxP with commissioning experience on at least two projects of equal or larger scope and complexity. Apply the text's qualified exception for CxP association on certain alterations.1
The CxP assists with OPR early, reviews the BOD, attends at least one design meeting and one construction milestone meeting, reviews submittals/substitutions for OPR impacts, and samples at least 10% of completed contractor QA/QC documentation.1
FAQ
Sources
This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.