SSp1 Minimize Site Disturbance

Assess and protect the site's vegetation and habitat, and implement erosion and sedimentation controls during construction.1

Points
Required
Applies to
BD+C

Reviewed · Spot an error? Report it

Points

Required for NC and Core and Shell; no points. Both the site assessment and implemented control plan are required.1

Documents to prepare

Prepared by VERTIQ as a checklist. Check the Reference Guide for what your review requires.

  • Preconstruction ecological/site assessment and vegetation survey
  • Habitat exclusion-zone and invasive-species control plan
  • Erosion and sedimentation control plan
  • Site-inspection, storm-event, dewatering, and corrective-action records
  • Compliance-route record for the erosion and sedimentation plan: permit applicability, named local equivalent, or compliance by plan
  • Landscape plan or equivalent evidence showing only native and adapted vegetation not listed as invasive

Worked example

Assume an assessment identifies 12 special-status trees. Protecting 11/12 = 91.67% does not satisfy the requirement to conserve 100% of special-status vegetation. This example does not replace the broader habitat and erosion-control obligations.1

Requirements

Survey special-status vegetation, healthy plant communities, and invasive species before construction. Conserve all special-status vegetation, establish physical exclusion zones for healthy habitat, and plan invasive-species control. Use only native/adapted vegetation that is not listed as invasive.1

Create and implement an erosion/sedimentation plan following the stated EPA 2022 CGP, EU Taxonomy noise/dust provisions, or local equivalent. Include habitat protection, inspections on the prescribed weekly or alternate storm-responsive schedule, daily dewatering inspections when discharge occurs, and immediate correction of failed controls. The CGP size exception is not used.1

FAQ

Can a small site omit erosion controls?

No. The prerequisite applies the stated control requirements regardless of project size.1

Sources

This reference summarizes the cited material. It does not replace the applicable rating system, addenda or a GBCI review.

  1. LEED v5 BD+C Rating SystemJuly 2026 · SSp1, printed pp. 35-36

Maintained by VERTIQ, LEED software for consultants.